Section 71
Times And Procedure Of Performing Contract
(1) In case the time and procedure of performing the contract has been mentioned in the contract, it shall be performed within the specified time and according to the specified procedure.
(2) In case no time or procedure of performing the work mentioned in the contract has been specified, whereas, in case the work can be performed only at any specific time or according to any specific procedure, the contract shall be deemed to have been concluded so as to perform the work at that time and according to that procedure.
(3) Except in the circumstances mentioned in Sub-section (2), in case the time and procedure of performing the contract has not been mentioned in the contract, the contract shall be performed within a reasonable time by adapting a reasonable procedure.